1 |
Sub- base, clean and clear of any loose debris. Lay polythene and fix perimetre edging strip. |
 |
2 |
Tape down all joints and pvc apron on perimeter edging strip to ensure there will be no grout loss. |
 |
3 |
Set-up floor levels using self levelling lazer and thread level indicators. |
 |
4 |
Flow test material. |
 |
5 |
Pour flowing screed to desired level (following thread level indicators.) |
 |
6 |
Remove tripods. |
 |
7 |
Finish and close surface using dappler bars. |
 |
8 |
Finished floor. |
 |